Warringah Freeway Upgrade

An upgrade of four kilometres of the Warringah Freeway between North Sydney and Naremburn, built in live traffic and due for completion in late 2026.

The Warringah Freeway Upgrade rebuilds about four kilometres of the Warringah Freeway between High Street at North Sydney and Willoughby Road at Naremburn. The freeway carries traffic to and from the Sydney Harbour Bridge and the Sydney Harbour Tunnel, and Transport for NSW says more than 250,000 people use the road network each day. At its widest point the freeway has up to 16 lanes.

Scope

  • New concrete barriers and a simpler lane layout, so that drivers merge and change lanes less often.
  • Improved interchanges at Falcon Street and High Street, including a new northbound on-ramp from High Street.
  • A continuous southbound bus lane from Miller Street to the Sydney Harbour Bridge.
  • About 2.5 kilometres of new and upgraded cycleways and footpaths, including new bridges over the freeway.
  • Connections for the future Western Harbour Tunnel.

Contract

Transport for NSW is the client. The design and construct contract went to a joint venture of CPB Contractors and Downer EDI Works. Downer's share moved to DT Infrastructure, which was Downer's transport projects business until Gamuda bought it in 2023. CPB Contractors holds 70 per cent of the joint venture and DT Infrastructure holds 30 per cent.

Timeline

The project received planning approval in January 2021, and early work started in March 2021. Because the work happens in live traffic, the crews changed lane layouts many times over almost five years. The last major changes, a permanent northbound lane between Lavender Street and Ernest Street and the High Street on-ramp, are due in December 2026. Landscaping and finishing work continue into 2027.

Heavy lifts

The new pedestrian and cycle bridges were lifted in during weekend and night closures. In May and June 2024, Borger Cranes set up its Liebherr LTM 1750-9.1 and LTM 1650-8.1 all-terrain cranes on the freeway to install pedestrian bridge sections of up to about 120 tonnes.

Companies on this project

Equipment on this project

Plan the equipment and transport for each project

Idalia links assets, allocations, and transport loads to each project, so the office and the site work from the same plan.

Explore projects

Idalia checked this page against its sources on 8 November 2026. Report a correction

Correct this page

Worked on this project, or see an error? Tell us what to change. We check each request against public sources.

We use your details only to answer this request.