Coffs Harbour Bypass
A 14-kilometre bypass of Coffs Harbour on the Pacific Highway, from Englands Road in the south to Sapphire in the north, with three road tunnels.
The Coffs Harbour Bypass takes Pacific Highway traffic around the Coffs Harbour urban area. The route runs about 14 kilometres from Englands Road in the south to Sapphire in the north, to the west of the city. It is part of the Pacific Highway upgrade, which the Australian and NSW governments fund.
Why the bypass is needed
The highway through Coffs Harbour is part of the Sydney to Brisbane freight route. In 2016 it carried between 30,000 and 35,000 vehicles a day on a 12-kilometre low-speed road with 12 sets of traffic lights, a major roundabout and 26 other intersections. The casualty rate on that road was more than three times the expected rate for a road of its class.
Scope
The project includes three road tunnels, at Gatelys Road, Shephards Lane and Roberts Hill, and 21 bridges. The longest bridge crosses the North Coast Railway line. Interchanges at Englands Road, Coramba Road and Korora Hill connect the bypass to local roads, and a new bus interchange at Korora opened in stages from September 2026. The route was realigned near Mackays Road to protect Grandpa's Scrub, a remnant of subtropical lowland rainforest. When the bypass opens, the old highway through the city becomes Solitary Islands Way.
Contract
Transport for NSW is the client. Ferrovial and Gamuda hold the design and construct contract as a joint venture. Ferrovial reports a contract value of A$1.5 billion, awarded in 2022.
Progress
By early 2026 the crews were fitting lighting, fire and safety systems in the three tunnels. By mid-2026 the work had moved from heavy earthworks to asphalt, noise walls, planting and structures for wildlife. Transport for NSW says the section between Englands Road and Korora will open to traffic at the end of 2026.
Heavy lifts
Borger Cranes supplied the large cranes for the project's big lifts, including bridge girders. In October 2024, in a night closure between midnight and 3 am, a crane rated at 650 tonnes lifted the 60-metre main span of the new Luke Bowen pedestrian bridge into place.
Companies on this project
- Transport for NSWClient
- FerrovialJoint venture partner
Design and construct contract, in a joint venture with Gamuda
- Gamuda AustraliaJoint venture partner
Design and construct contract, in a joint venture with Ferrovial
- Borger CranesSubcontractor
Crane hire for heavy lifts, including bridge girders and the Luke Bowen pedestrian bridge
Equipment on this project
Related projects
- Sydney Metro WestUnder construction · Westmead to Sydney CBD, NSW
A 24-kilometre underground metro railway between Westmead and Hunter Street in the Sydney CBD, with nine stations and a target opening in 2032.
- Warringah Freeway UpgradeUnder construction · North Sydney, NSW
An upgrade of four kilometres of the Warringah Freeway between North Sydney and Naremburn, built in live traffic and due for completion in late 2026.
- Botany Rail DuplicationCompleted · Mascot to Port Botany, NSW
A second track on the last 2.9-kilometre single-track section of the freight rail line between Mascot and Port Botany, with four new rail bridges.
- M12 MotorwayCompleted · Luddenham to Cecil Hills, NSW
A 16-kilometre toll-free motorway between the M7 at Cecil Hills and The Northern Road at Luddenham, and the main road access to Western Sydney International Airport.
- Western Harbour TunnelUnder construction · Rozelle to North Sydney, NSW
A 6.5-kilometre motorway tunnel under Sydney Harbour, with three lanes each way, between the Rozelle Interchange and the Warringah Freeway near North Sydney.
- Sydney Metro – Western Sydney AirportUnder construction · St Marys to Bradfield, NSW
A 23-kilometre metro railway from St Marys to Bradfield City Centre through Western Sydney International Airport, with six stations.
Plan the equipment and transport for each project
Idalia links assets, allocations, and transport loads to each project, so the office and the site work from the same plan.
Idalia checked this page against its sources on 8 November 2026. Report a correction
Correct this page
Worked on this project, or see an error? Tell us what to change. We check each request against public sources.