Coffs Harbour Bypass

A 14-kilometre bypass of Coffs Harbour on the Pacific Highway, from Englands Road in the south to Sapphire in the north, with three road tunnels.

The Coffs Harbour Bypass takes Pacific Highway traffic around the Coffs Harbour urban area. The route runs about 14 kilometres from Englands Road in the south to Sapphire in the north, to the west of the city. It is part of the Pacific Highway upgrade, which the Australian and NSW governments fund.

Why the bypass is needed

The highway through Coffs Harbour is part of the Sydney to Brisbane freight route. In 2016 it carried between 30,000 and 35,000 vehicles a day on a 12-kilometre low-speed road with 12 sets of traffic lights, a major roundabout and 26 other intersections. The casualty rate on that road was more than three times the expected rate for a road of its class.

Scope

The project includes three road tunnels, at Gatelys Road, Shephards Lane and Roberts Hill, and 21 bridges. The longest bridge crosses the North Coast Railway line. Interchanges at Englands Road, Coramba Road and Korora Hill connect the bypass to local roads, and a new bus interchange at Korora opened in stages from September 2026. The route was realigned near Mackays Road to protect Grandpa's Scrub, a remnant of subtropical lowland rainforest. When the bypass opens, the old highway through the city becomes Solitary Islands Way.

Contract

Transport for NSW is the client. Ferrovial and Gamuda hold the design and construct contract as a joint venture. Ferrovial reports a contract value of A$1.5 billion, awarded in 2022.

Progress

By early 2026 the crews were fitting lighting, fire and safety systems in the three tunnels. By mid-2026 the work had moved from heavy earthworks to asphalt, noise walls, planting and structures for wildlife. Transport for NSW says the section between Englands Road and Korora will open to traffic at the end of 2026.

Heavy lifts

Borger Cranes supplied the large cranes for the project's big lifts, including bridge girders. In October 2024, in a night closure between midnight and 3 am, a crane rated at 650 tonnes lifted the 60-metre main span of the new Luke Bowen pedestrian bridge into place.

Companies on this project

Equipment on this project

Plan the equipment and transport for each project

Idalia links assets, allocations, and transport loads to each project, so the office and the site work from the same plan.

Explore projects

Idalia checked this page against its sources on 8 November 2026. Report a correction

Correct this page

Worked on this project, or see an error? Tell us what to change. We check each request against public sources.

We use your details only to answer this request.