Sydney Metro West

A 24-kilometre underground metro railway between Westmead and Hunter Street in the Sydney CBD, with nine stations and a target opening in 2032.

Sydney Metro West is a new underground metro railway between Westmead and the Sydney CBD. It will double rail capacity between Parramatta and the CBD. The line has nine stations: Westmead, Parramatta, Sydney Olympic Park, North Strathfield, Burwood North, Five Dock, The Bays, Pyrmont and Hunter Street. Sydney Metro targets an opening in 2032.

At 24 kilometres, the twin tunnels are the longest rail tunnels in Australia. Sydney Metro reports that six tunnel boring machines excavated them, and that more than 22,900 people worked on the tunnelling.

Tunnelling contracts

Sydney Metro divided the tunnels into three design and construct packages.

  • Western Tunnelling Package. About 9 kilometres of twin tunnels between Westmead and Sydney Olympic Park, excavation for Parramatta and Westmead stations, and civil work for the Clyde stabling and maintenance facility. Gamuda and Laing O'Rourke hold the A$2.16 billion contract.
  • Central Tunnelling Package. Twin 11-kilometre tunnels from The Bays to Sydney Olympic Park, and excavation for five stations. ACCIONA and Ferrovial won the $1.96 billion contract in July 2021.
  • Eastern Tunnelling Package. Tunnels from The Bays to Hunter Street, a turnback cavern east of Hunter Street, and the mined station caverns at Pyrmont and Hunter Street. John Holland, CPB Contractors and Ghella won the $1.63 billion contract in November 2022.

The Western and Central packages each include a precast segment facility at Eastern Creek.

Stations and systems

Gamuda holds the Stations Package West contract, the first station contract, for five underground stations at Westmead, North Strathfield, Burwood North, Five Dock and The Bays. John Holland holds the Linewide Package, for about 60 kilometres of track, the rail systems and the 38-hectare stabling and maintenance facility at Clyde. The Metro Trains West Consortium, led by MTR, will supply 16 trains and operate the line for 15 years after it opens.

With tunnelling complete, the next stage is tunnel fit-out: track, power, ventilation, communications and safety systems.

Companies on this project

Plan the equipment and transport for each project

Idalia links assets, allocations, and transport loads to each project, so the office and the site work from the same plan.

Explore projects

Idalia checked this page against its sources on 8 November 2026. Report a correction

Correct this page

Worked on this project, or see an error? Tell us what to change. We check each request against public sources.

We use your details only to answer this request.