Botany Rail Duplication
A second track on the last 2.9-kilometre single-track section of the freight rail line between Mascot and Port Botany, with four new rail bridges.
The Botany Rail Duplication added a second track to the last single-track section of the Botany freight line in Sydney. The section is 2.9 kilometres long and runs between Mascot and Port Botany, past Sydney Airport. The Australian Rail Track Corporation (ARTC) delivered the project for the Australian Government.
Why it was needed
The single-track section limited how many freight trains could reach Port Botany. ARTC expects the line to carry about 45 trains a day in each direction by 2030, up from an average of about 20. One train can carry about the same number of containers as 54 trucks, so more freight on rail means fewer trucks on Sydney roads. Container freight through Port Botany is forecast to grow by 77 per cent between 2016 and 2036.
Scope
- A new track in the rail corridor for 2.9 kilometres, and realignment of the existing track.
- New and replacement rail bridges at Mill Stream, Southern Cross Drive, O'Riordan Street and Robey Street.
- New crossovers, so that trains can move between the tracks.
- Embankments and retaining structures.
- Bi-directional signalling, drainage, and protection or relocation of utilities.
Contract and timeline
John Holland was the design and construct contractor, from November 2021 to April 2024. Major construction started in early 2022, and ARTC commissioned the new track in January 2024. ARTC delivered the project with the Cabramatta Loop, which Fulton Hogan built. The Australian Government funded the two projects with $442 million.
Heavy lifts
To replace the Robey Street rail bridge, John Holland and Borger Cranes removed the old bridge in a single 160-tonne lift. The bridge was old, access was restricted, and the team had to coordinate with stakeholders including Sydney Airport. The lift was runner-up for the Crane Industry Council of Australia's Lift of the Year award for lifts of more than 20 tonnes.
Companies on this project
Equipment on this project
Related projects
- Sydney Metro WestUnder construction · Westmead to Sydney CBD, NSW
A 24-kilometre underground metro railway between Westmead and Hunter Street in the Sydney CBD, with nine stations and a target opening in 2032.
- M12 MotorwayCompleted · Luddenham to Cecil Hills, NSW
A 16-kilometre toll-free motorway between the M7 at Cecil Hills and The Northern Road at Luddenham, and the main road access to Western Sydney International Airport.
- Warringah Freeway UpgradeUnder construction · North Sydney, NSW
An upgrade of four kilometres of the Warringah Freeway between North Sydney and Naremburn, built in live traffic and due for completion in late 2026.
- Western Harbour TunnelUnder construction · Rozelle to North Sydney, NSW
A 6.5-kilometre motorway tunnel under Sydney Harbour, with three lanes each way, between the Rozelle Interchange and the Warringah Freeway near North Sydney.
- Coffs Harbour BypassUnder construction · Coffs Harbour, NSW
A 14-kilometre bypass of Coffs Harbour on the Pacific Highway, from Englands Road in the south to Sapphire in the north, with three road tunnels.
- Sydney Metro – Western Sydney AirportUnder construction · St Marys to Bradfield, NSW
A 23-kilometre metro railway from St Marys to Bradfield City Centre through Western Sydney International Airport, with six stations.
Plan the equipment and transport for each project
Idalia links assets, allocations, and transport loads to each project, so the office and the site work from the same plan.
Idalia checked this page against its sources on 8 November 2026. Report a correction