Overview
When plant has to work on a job, it needs to get there and back. That could be as easy as a single truck trip, or a multi-stage logistics package spanning multiple countries and modes of transport. Idalia makes it easy to plan, track and forecast these logistics, no matter how complex they are. This guide follows the example of a tower crane, currently in a storage yard in Sydney, being booked to a job in Portugal. We’ll see how we can use Idalia to manage all the logistics needed for the job end-to-end. There’s three parts to this workflow:- Decide which assets are needed for the job.
- Create the logistics plan: first at a high level, then in detailed, sequenced delivery steps.
- Update the plan as each stage is completed, and track the progress of the whole trip.
Lisbon tower crane. Add the crane once and it shows up on every leg. Road legs are transport orders, the sea booking is a shipment, and the time the crane spends on the job is an allocation.
If all you need is a single truck onto a nearby site, you don’t need a journey. Use Last-mile site delivery instead.
Who does each part of the work?
A move like this has a lot of people in it. The below table shows who does what, and where they record it.What do you need before you start?
You’ll need the Portugal job set up, with a site and dates the crane has to be there — the project coordinator agrees those with the site supervisor. You’ll also need the Sydney yard, Port Botany, and Lisbon port as places, and the crane on the books, including any mast section or counterweight that travels as its own unit. In Idalia those are a project, locations, and the asset register. If the parts travel separately, see Assemblies.How do you name the trip and list the plant?
The transport coordinator opens Journeys and creates a journey namedLisbon tower crane. Point it at the Portugal job, and set the owner to whoever is running the move.
Then open Assets and choose Add assets. Add the crane, plus any section or counterweight that travels on its own. Do this before you add the legs, so each new stage already includes the plant.
That’s the trip named, owned, and loaded with the right assets.
How do you plan the legs?
This is the high-level plan first, then the sequenced delivery steps. On Stages, choose Add stage, pick Transport order, Shipment, or Allocation, then Create new so the document stays on this journey. For the Lisbon crane, the stages look like this:
On each road leg, set the pickup and the drop-off.
On each sea leg, choose Ocean. The freight forwarder holds the booking; you enter the MBL No. so status can come through from the carrier.
On the time on the job, the project coordinator sets the dates from the day the crane has to be on site to the day it leaves.
If a stage is in the wrong order, drag it. Keep the trip home on
Lisbon tower crane — a road order, a sea booking, or a job booking can only sit on one journey, and splitting the return would split the same move.
How do you run the trip?
As each stage completes, update the plan so you can see where the crane is and what’s still ahead. You set the road orders and read the sea bookings. The project coordinator sets the time on the job. Planned, In Progress, and Completed are the default names. Your workspace might use other words for booked, on the move, and finished.- The yard supervisor finishes loading at the Sydney yard. Set that load to Loading.
- The driver leaves. Set the load to In Transit, and the road order to In Progress.
- The truck arrives at Port Botany. Set the load and the road order to Completed.
- Watch the shipment until the crane is at Lisbon port. The carrier supplies that status.
- Run the trucks to the site. The site supervisor confirms the crane is there.
- The project coordinator sets the allocation to In Progress.
- The site releases the crane. The project coordinator sets the allocation to Completed.
- Run the three return legs the same way. The last drop-off is the Sydney yard.
How do you check the result?
OnLisbon tower crane, the same crane is on all seven stages, the last drop-off is the Sydney yard, and every stage is Completed. That’s the whole trip, planned and tracked end-to-end.
Common questions
Do you put the sea freight on a road order?
No. A transport order is a road leg. The sea booking is a shipment, and the freight forwarder runs it. You add that shipment as a stage on the journey.Can the trip home be a second journey?
Keep it onLisbon tower crane. The crane is one line on every stage, including the return. A second journey would split the same move in two.