# Dependent dates

> Keep a date in step with the start or end of another record.

A dependent date follows the start or end of another record. When that source date changes, Idalia updates the date that follows it.

You can link a date on a project, a work order, an allocation order, or a transport order. The source can be one of those records too.

![A work order start date linked to a project start date](https://mintcdn.com/idalia-e4cdca17/Fszt6qeOM3ra2MK6/images/dates-depends-light.png?fit=max\&auto=format\&n=Fszt6qeOM3ra2MK6\&q=85\&s=48dff1df003c072cb03d024a7802202a)

## Link a date

1. Open the project, work order, allocation order, or transport order.
2. Select the start date or the end date. The menu title is **Select date**.
3. Press the **Link date** control. The title changes to **Link date**.
4. Choose the record type: **Projects**, **Work Orders**, **Allocation Orders**, or **Transport orders**.
5. Choose the record.
6. Choose the date on that record: start or end.
7. Press <kbd>Enter</kbd>.

The linked date updates when the source date changes.

## Add an offset

An offset moves the linked date by a set amount. The climb can start one month after the project starts. The dismantle can start when the project ends, with no offset.

![A linked date with a one month offset](https://mintcdn.com/idalia-e4cdca17/Fszt6qeOM3ra2MK6/images/dates-offset-light.png?fit=max\&auto=format\&n=Fszt6qeOM3ra2MK6\&q=85\&s=a45a2fa6557b4944f22ddfc1e995eedc)

1. Follow [Link a date](#link-a-date) through step 6.
2. Press <kbd>Shift</kbd> + <kbd>Enter</kbd>. The footer shows this shortcut as **for offset**.
3. Set the amount with the left and right arrows. A positive amount is after the source date. A negative amount is before it.
4. Set the unit: **Minutes**, **Hours**, **Days**, **Weeks**, **Months**, or **Business Days**.
5. Press <kbd>Enter</kbd>.

## Remove a link

1. Open the date. The menu title is **Linked date**.
2. Press <kbd>Remove link</kbd>.

Pick a fixed date in the same menu to clear the link. The menu also has **Swap direction** and **Re-apply from source**.

## Cycles

A cycle is a loop. The install starts when the climb starts, the climb starts when the dismantle starts, and the dismantle starts when the install starts. That loop is not a valid schedule.

![Three dates that depend on each other in a loop](https://mintcdn.com/idalia-e4cdca17/Fszt6qeOM3ra2MK6/images/dates-cycles-light.png?fit=max\&auto=format\&n=Fszt6qeOM3ra2MK6\&q=85\&s=0f454c40ec4d8903a842c473904b9f3f)

Idalia leaves a record out of the list when a link to it would make a loop. A date cannot link to its own record.

## Crane example

A tower crane stays on a site from 1 January to 31 March. The job has three work orders: install, climb, and dismantle. The climb starts one month after the project starts. Fifty crane parts are on site for the whole job. Four tower sections arrive for the climb.

1. Create the project. Set the start to 1 January and the end to 31 March.
2. Create the install work order. Link its start to the project start.
3. Create the climb work order. Link its start to the project start, with an offset of 1 month.
4. Create the dismantle work order. Link its start to the project end.
5. Create the allocation order on the project. Link its start to the project start, and its end to the project end.
6. Add the 54 parts to the allocation order. Each line follows the allocation order dates while **Dates linked** is on.
7. For the four tower sections, right-click the line and turn **Dates linked** off. Drag the line on the allocation timeline so it starts with the climb work order. Those dates stay on the days you set.

When the project start moves back one week:

* The install work order, the climb work order, and the allocation order move with it.
* The 50 lines that still have **Dates linked** on move with the allocation order.
* The four tower sections stay on the days you set in step 7.