# Placeholders

> Book a kind of plant before you pick the machine.

A placeholder is one line for an [asset type](https://useidalia.com/docs/assets/types.md) when the asset is not chosen yet. Use it on an [allocation order](https://useidalia.com/docs/allocations/introduction.md) or a [transport order](https://useidalia.com/docs/logistics/transport.md).

The line keeps its dates, status, and notes. When you assign an asset, those stay on the line.

![A placeholder line for an asset type on an allocation](https://mintcdn.com/idalia-e4cdca17/Fszt6qeOM3ra2MK6/images/placeholders-light.png?fit=max\&auto=format\&n=Fszt6qeOM3ra2MK6\&q=85\&s=28bea1d03f56eab79cd6c994ad029c3e)

## Add a placeholder

1. Open the allocation order.
2. Press <kbd>Add assets</kbd>.
3. Select the asset type.
4. Under **Placeholders**, press **+** to add one line for that type. You can add up to 100.
5. Close the panel. The line shows **Placeholder** until you assign an asset.

On an assembly type, a placeholder splits the assembly into its parts so you can assign each part. See [Assemblies](https://useidalia.com/docs/assets/assemblies.md).

On a transport order, drag the placeholder from the asset register onto a route. See [Transport](https://useidalia.com/docs/logistics/transport.md).

## Assign the asset

1. On the allocation order, select the placeholder name on the line.
2. The menu title is **Assign asset**.
3. Select the asset.

The dates, status, and notes stay on the line.

On a transport order, right-click the placeholder line and choose **Select asset**.

## Crane example

The Portugal job needs one tower crane from 1 January to 31 March. The machine is not chosen yet. The type is.

1. Create the allocation order on the project.
2. Add one placeholder for the tower crane asset type.
3. Link the allocation start to the project start, and the end to the project end. See [Dependent dates](https://useidalia.com/docs/projects/dependent-dates.md).
4. When you know which crane will go, select the placeholder and assign that crane.

The linked dates stay on the line. A later change to the project start moves the allocation, and the assigned crane moves with it.